Does lockout/tagout apply on a construction site, or only in general industry?

Quick answer

Construction has its own, much shorter rule. For electrical work, controls to be deactivated must be tagged (29 CFR 1926.417(a)), deenergized equipment and circuits must be rendered inoperative and tagged at every point where they could be energized (1926.417(b)), and tags must plainly identify what is being worked on (1926.417(c)). The detailed general-industry program — written procedures, annual inspections, authorized-employee training — is 1910.147, which by its own scope covers general industry, not construction (29 CFR 1910.147(a)(1)(i)). Many contractors adopt it anyway, because it is the fuller answer to the same hazard.

"Do I need a LOTO program on the jobsite?" has a legal answer and a practical one, and they are not the same.

The construction rule. Subpart K's lockout and tagging provision is three sentences. Controls that are to be deactivated during work on energized or deenergized equipment or circuits must be tagged (29 CFR 1926.417(a)). Equipment or circuits that are deenergized must be rendered inoperative and have tags attached at all points where they can be energized (29 CFR 1926.417(b)). Tags must be placed to identify plainly the equipment or circuits being worked on (29 CFR 1926.417(c)). There is no construction-wide requirement for written energy-control procedures, periodic inspections, or locks — the word "lock" does not appear.

Where 1910.147 does and doesn't reach. The general-industry control-of-hazardous-energy standard covers servicing and maintenance of machines and equipment where unexpected energization or release of stored energy could injure employees (29 CFR 1910.147(a)(1)(i)), and its scope expressly excludes construction. A contractor servicing its own shop equipment is in 1910.147; the same mechanic on a jobsite is in Part 1926.

Why contractors use 1910.147 anyway. The hazard — a conveyor, a batch plant, a pump restarting with someone inside it — is identical, and the General Duty Clause still requires a workplace free of recognized hazards likely to cause death or serious harm (OSH Act §5(a)(1)). A written procedure with locks, verification and training is the recognized way to control that hazard, which is why it is the common answer even where only 1926.417 is cited.

On a multi-employer site the practical rule is the host's rule. If the facility runs a 1910.147 program, the contractor follows it; if the contractor's own equipment is the hazard, the contractor brings the program.

29 CFR 1926.417(a)29 CFR 1926.417(b)29 CFR 1926.417(c)29 CFR 1910.147(a)(1)(i)OSH Act §5(a)(1)
Source: An analysis from the construction electrical standard's lockout and tagging provision (29 CFR 1926.417) read against the general-industry control of hazardous energy standard (1910.147). Primary reference: read it on osha.gov →

Federal rule shown. If the workplace is in one of the 29 State Plan states and territories, the state standard governs and may differ — see Known Limitations.

Need the passage itself?

Canary AI has indexed all of federal OSHA — 7,220 passages of 29 CFR and 279 interpretation letters — and finds the exact section for a question, with a link to the official text. Free, no sign-up, nothing collected.

Open the lookup tool →

Related answers

What does the annual lockout/tagout 'periodic inspection' actually have to include?Lockout/Tagout · standards analysisCan a machine be re-energized during servicing when the task requires power?Lockout/Tagout · OSHA letter 2024-10-21Can a supervisor's lock cover the whole crew in a group lockout/tagout?Lockout/Tagout · OSHA letter 2021-05-21